Tiree Linkspan Replacement

Those of you attended the CMAL /CalMac Meeting  3 Sept 2019 would have seen this video

It shows the modus operandi of the Oban linkspan replacement from  leaving Glasgow to its  installation in Oban

The same modus operandi will apply next year to the Tiree linkspan replacement .

The heavy lift operation, putting the linkspan in place ,can take place in wind conditions up to Beaufort 5,  although sea conditions  and other issues will dictate when the the BIG LIFT actually takes place.

It only needs a narrow weather window to put the l/span in place.The ancillary works take most of the time-span.

CMAL have factored in a 10 day contingency margin , based on 10 year historical weather data  which explains  CMAL’s confidence in the Tiree project not exceeding  the current 24 Feb-16 Mar  outage period’.

CalMac’s presentation, re the proposed freight-only  ferry service freight, did not offer similar confidence.