CMAL repair plans for the Old Pier

CMal held a pop-in presentation at the Pier office on Wed 15th May outlining their proposed repair works (£800K) for the Old Pier to be completed this summer.

CMal presentation for Old Pier 15 may 2019

Originally the Old Pier was to be used to facilitate Tiree’s  LinkSpan replacement planned for the weeks prior to Easter 2020 , but use of the Old Pier has been’ engineered‘ out of the project and will only be used to store the linkspan over the winter .

The Tiree l/span  is currently  being fabricated.It will be shipped to Tiree at the same time as the Coll replacement l/span which is being replaced this autumn.